Stanmore awards $363.58m extension to Golding at Isaac Plains East

Published by Mining Technology - 18th Nov 2018

Stanmore Coal has awarded Golding Contractors an A$500m ($363.58m) extension to the existing mining services contract at Isaac Plains East coal mine in Queensland, Australia.

Read More
DBCT Output - Year Comparison 

Published by ILC - 12th February 2018

2017 saw reasonable throughput year for the supply chain of 65,149,253t.  The 4 week closure of the rail network in April due to Cyclone Debbie impacted on the system throughput.

Annual Total 2014 2015 2016
2017
Coal Chain Throughput 69,947,368t 69,686,774t 68,869,087t 65,149,253t
Total Vessels 668 668 681 631
Avg. Shipment Size
104,555t 104,322t
100,686t
103,248t
Total Trains 7,162 7,087 6,972 6,586
Average Payload 9,746t 9,865t 9,885t 9,887t